Commercial & Industrial Electrician

Commercial Generator Testing: Weekly, Monthly, and Annual Checks

Written by Michael Zilliox | Nov 10, 2026, 8:51:59 PM

If your building or plant has a standby generator, this guide explains what has to be inspected and tested, how often, and what to record. It also explains why a generator that rarely carries much load may need an extra annual test, and when a problem during a test calls for an electrician or the generator dealer. A monthly test log is at the end.

The short answer

For generators covered by NFPA 110:

  • Weekly: Inspect the system. Under the 2025 edition, Level 2 systems may be inspected monthly instead.
  • Monthly: Run the generator under load for at least 30 minutes, and operate each transfer switch.
  • Annually: Run a load bank test if the generator did not carry enough load during its monthly runs.
  • Every 36 months: Run a longer test on Level 1 systems.
  • Always: Record every inspection, test, and repair.

First, find out what kind of system you have

NFPA 110, the Standard for Emergency and Standby Power Systems, applies when a code requires an emergency power supply system and points to the standard. The standard sorts systems into two levels:

  • Level 1: Failure could cause loss of life or serious injury. Examples include generators serving emergency egress lighting or life safety systems.
  • Level 2: Failure is less critical to life and safety, such as legally required standby loads.

Many commercial generators are optional standby systems, installed to keep a business running rather than because a code requires them. For those systems, the manufacturer's maintenance schedule usually governs, though many owners follow the NFPA 110 routine anyway because it is a proven program.

Not sure which you have? Your generator's installation records, your fire code official, or your electrical contractor can tell you.

The current edition of NFPA 110 is 2025, but your jurisdiction may enforce an older edition referenced by its adopted fire or building code. The schedule below follows the 2025 edition. Where an earlier edition differs in a way that matters, it is noted.

Weekly inspection

NFPA 110 calls for Level 1 systems to be inspected weekly. The 2025 edition allows monthly inspections for Level 2 systems. Because older editions required weekly checks for both levels, plan on weekly inspections unless your fire code official tells you otherwise.

A typical weekly walk-around checks:

  • Fuel level, and for diesel units, signs of leaks
  • Oil and coolant levels, following the manufacturer's procedure
  • Battery condition, charger operation, and alarm indicators
  • That the generator control is set to automatic
  • That the transfer switch is in its normal position, with no alarms
  • That the enclosure, air intake, and exhaust are clear of debris

Monthly exercise under load

Each generator set should run at least monthly, for at least 30 minutes, under load. The 30 minutes is counted from when the generator takes the load, not from when it starts.

For diesel units, the load must do one of two things. It must keep the exhaust at the manufacturer's recommended minimum temperature, or it must reach at least 30 percent of the generator's standby nameplate kW rating. Natural gas and other spark-ignited units run with whatever emergency system load is available.

Also operate transfer switches monthly by electrically moving them from normal power to the generator and back. If you have several transfer switches, rotate which one starts the monthly test.

Why light loading matters: wet stacking

Generators are often sized for future growth, so a building's real emergency load may be well under 30 percent of the generator's rating. A diesel engine that repeatedly runs lightly loaded doesn't burn its fuel completely. Unburned fuel and carbon build up in the exhaust, a condition called wet stacking. Over time, it reduces performance and can lead to failures.

That is why NFPA 110 adds an annual supplemental load test when monthly runs don't reach the required load.

Annual load bank test, if your monthly runs fall short

A diesel unit that cannot meet the monthly loading rule must still be exercised every month on the available load. It then needs one supplemental load test each year.

Under the 2025 edition, the generator runs at least 50 percent of nameplate kW for 30 continuous minutes, then at least 75 percent for 60 continuous minutes, for a total of 1.5 hours. Earlier editions started with an extra step at 25 percent, for a two-hour total.

A portable load bank provides the extra load. If your generator carries at least 30 percent of its nameplate rating, or reaches the manufacturer's exhaust temperature, during every monthly run, this annual test is not required. Your monthly log is the evidence, which is one more reason to record kW during every run.

The 36-month test for Level 1 systems

At least once every 36 months, a Level 1 system must run continuously for the duration of its class rating. The test may stop after four continuous hours.  Plan this one ahead, because it is the longest run in the schedule.

Records

NFPA 110 requires a record of every inspection, test, exercise, repair, and modification, available to the authority having jurisdiction. For the monthly run, record at least:

  • The hour meter reading
  • How the test was started
  • Start and transfer times
  • Voltage, frequency, amps, and kW under load
  • Oil pressure, battery charging rate, and coolant temperature
  • The retransfer time

The log below follows that sequence.

When to call an electrician or the generator dealer

Stop and call for service when:

  • The generator fails to start, or starts slowly or only after several tries.
  • The transfer switch does not transfer, takes noticeably longer than usual, or does not return to normal power.
  • Voltage or frequency is unstable under load.
  • An alarm or shutdown occurs during the test.
  • Monthly runs never reach 30 percent of nameplate kW, and no annual load bank test is scheduled.
  • You see fuel or oil leaks, black smoke, or signs of wet stacking.
  • You plan to add load to the generator, or the building's emergency loads have changed.

Who to call depends on the problem. Generator work is usually split three ways:

  • Generator dealer: The engine (oil, coolant, and engine controls), transfer switch service, and load bank testing.
  • Plumbing contractor: Fuel piping to the generator.
  • Licensed electrician: Generator installation, wiring, breakers, load connections, and changes to which loads the generator serves.

If you aren't sure where a problem starts, call the company that installed the system. They can tell you which trade it belongs to.

 

Download the Monthly Generator Test Log Spreadsheet

 

What you can do, and what needs a professional

Trained facility staff can do the weekly inspection, start and watch the monthly run following the manufacturer's procedure, record readings, and keep the log. Load bank testing and transfer switch maintenance need the generator dealer. Fuel piping needs a plumbing contractor. Breaker work, wiring repairs, and changes to the system's loads need a licensed electrician.

How CDI Electric can help

CDI Electric installs and services Kohler, Generac, CAT, and Cummins Onan generators for commercial and industrial facilities across Northern Kentucky and Greater Cincinnati.

We handle the electrical side of the system: wiring, breakers, load connections, and changes to which loads the generator serves.

The generator dealer handles engine service, transfer switch service, and load bank testing, and a plumbing subcontractor installs fuel piping.

CDI coordinates with both so the system is installed and tested as one job. If your generator is failing tests, isn't carrying enough load, or needs to support new equipment, see our commercial electrical services or industrial electrical services.

You can also call 859-291-9189.